SOI II Structural Steel and Slab Cont’d

School of Innovation structural steel and building slab continues. Most of the beams and columns for Area “A” have been installed and the bar-joists are being set. Area “B” & “C” slabs have been poured. The contractor is preparing to pour Area “D”.