All of the structural steel has been erected. Metal studs and drywall are being installed. Paint is being installed.The mechanical, electrical, and plumbing, are being installed.
Blog
SOI II PAC Structural Steel
The structural steel for the performing arts center wing is nearing completion. The mechanical, electrical, plumbing, and interior finishes are being installed in the other wings of the building.
SOI II Structural Steel & PAC Retaining Wall
Structural steel installation continues in Area “C”. The performing arts center retaining wall has been poured and the forms removed. Duct work, electrical, and plumbing installation continues in Areas “A” & “B”. Some masonry walls have been laid out in Area “C”.
SOI II Structural Steel and Auditorium Retaining Wall
Structural steel installation continues; installation has advanced to Area “C”. Except for the Performing Arts Center(PAC), all of the concrete slabs have been poured. Form work for the retaining wall of the PAC auditorium is being installed. Metal stud framing , electrical conduit, Duct work, and masonry are being installed,
SOI II Structural Steel and Slab
Structural steel erection continues. Area “F” slab has been poured; only Area “E” slab remains to be poured. The performing arts center auditorium undercut has begun. Plumbing, electrical, HVAC, and polish concrete installation continues.
SOI II Structural Steel and Slab Prep
Structural steel installation continues. Slab preparations continue. Mechanical, electrical, and plumbing installation continue. The masonry installation has begun.
SOI II Structural Steel and Concrete
The project is going well. Structural steel installation continues. Slab installation continues. Plumbing, Electrical, and HVAC are being installed in Area “A”.
SOI II Structural Steel & Slab
The school of innovation phase II continues. Structural steel installation continues at Area “A”. Slab preparations continue in Area “D”. Area “B & C” slabs have bee poured.
SOI II Structural Steel and Slab Cont’d
School of Innovation structural steel and building slab continues. Most of the beams and columns for Area “A” have been installed and the bar-joists are being set. Area “B” & “C” slabs have been poured. The contractor is preparing to pour Area “D”.
SOI II Slab and Structural Steel
Area “A” structural steel is being erected. Area “B” slab has been poured and is being cured. Area “C” slab prep has begun. Area “D” base gravel is being installed. Area “E & F” building pad has been completed.